After more than a month and a half of intense work, Fascene Airport Nosy Be now sports a new look. The renovation of the track has been completed and has been the subject of a technical acceptance the 30 October 2017.

This work concerned in particular the increase in capacity, the development of commercial areas and cleaning facades and renovation of the track. These new arrangements should ensure the safety of passengers and enhance the attractiveness of the Nosy-Be airport that should entice new international companies and attract more tourists.

This first phase of expansion of Nosy-Be airport, will have an investment of 15 millions of euros, 1 350 tons of bitumen and 20 000 tonnes of asphalt. The second step is already underway, concerns nozzle works, water treatment plant, Development of parking Nosy Be airport and refurbishment of Terminal.

And not to disturb or cancel flights, Ravinala Airports in charge of the operation of this site, decided to carry out the work only between 19 hours 7 hours of the morning. Work that will not fully completed until August 2018.

Manga Soa Lodge
Book Now

Manga Soa Lodge

Befefika Nosy Be 207 Madagasscar

from 546.000With /night

Villa Valiha Lodge
Book Now

Villa Valiha Lodge

Villa Valiha Lodge, Madirokely, Madagascar

from 331.500With /night

Hotel ** Le Grand Bleu
Book Now

Hotel ** Le Grand Bleu

BP407 Andilana Nosy-Be207 Madagascar

from 144.300With /night

Top Lodge
Book Now

Top Lodge

Amporaha Nord, Nosy Be 209

from 507.000With /night